North Carolina auditor: 84 state-run IT projects well over budget, schedule

Expert: State officials face a 'rat's nest' of work to fix IT project planning problems

Scores of IT projects being conducted by North Carolina's government are racking up higher-than-expected costs and going far beyond their planned schedules, a new report by the state's auditor has found.

Auditor Beth Wood's office surveyed 84 IT projects in the state and found that on average, the actual costs were more than double the original estimates and they took 65 percent longer than planned to complete, according to the audit released this week.

The cost overruns totaled US$356.3 million, according to the report.

While restrained in its tone, the audit paints a portrait of dysfunction and lack of oversight associated with the state's IT projects.

For one thing, the Office of Information Technology Services doesn't have a standard method state agencies can use to develop project estimates, according to the report. Nor are there any policies that provide for independent verification of a project estimate after it's made.

In addition, "state agency managers are not required to manage IT projects so that the projects meet the initial cost or schedule estimates that are submitted," the report adds.

The office also doesn't have any measures in place to ensure that it has accurate and complete data regarding IT project oversight. For example, the 84 implementations were chosen because out of more than 1,000 projects contained in the state's IT project portfolio management software, they were the only ones that had the "original cost and schedule estimate data" needed for an audit.

However, the ITS office may be hamstrung in one way, given that it "may not have the authority it needs to ensure that state agencies submit project status reports in a timely manner," the report states.

In a response attached to the report, ITS officials said they agreed with the findings and would work on improvements, including the requirement that state agencies get independent analyses of their project estimates.

But it stopped short of endorsing the auditor's suggestion that ITS ask the legislature pass a law holding state agency managers accountable for meeting budget and schedule estimates, saying instead that "a possible solution is better reporting and enforcement of existing law."

Overall, the audit presents a mixed bag for North Carolina, according to one observer.

"The report is basically saying that the finger to the wind method of estimating projects is not working," said analyst Michael Krigsman, CEO of Asuret and an expert on why IT projects struggle and even fail.

Meanwhile, the apparent willingness by ITS to seek reforms is "a double-edged sword," Krigsman said. "It means [ITS] has been lacking but also means they recognize and accept there's a problem. The lack of defensiveness is very positive."

The question now is what steps North Carolina can take to right the ship. Simply hiring independent people to validate estimates won't solve the problem, Krigsman said. "The difficult part is uncovering the information that's needed in order to make an accurate estimate. That's where you get a rat's nest."

Chris Kanaracus covers enterprise software and general technology breaking news for The IDG News Service. Chris' email address is Chris_Kanaracus@idg.com

Join the newsletter!

Or

Sign up to gain exclusive access to email subscriptions, event invitations, competitions, giveaways, and much more.

Membership is free, and your security and privacy remain protected. View our privacy policy before signing up.

Error: Please check your email address.

Tags governmentIT managementCIO roleservicessoftwareit strategyGovernment use of IT

Keep up with the latest tech news, reviews and previews by subscribing to the Good Gear Guide newsletter.

Chris Kanaracus

IDG News Service
Show Comments

Cool Tech

Toys for Boys

Family Friendly

Stocking Stuffer

SmartLens - Clip on Phone Camera Lens Set of 3

Learn more >

Christmas Gift Guide

Click for more ›

Brand Post

Most Popular Reviews

Latest Articles

Resources

PCW Evaluation Team

Aysha Strobbe

Microsoft Office 365/HP Spectre x360

Microsoft Office continues to make a student’s life that little bit easier by offering reliable, easy to use, time-saving functionality, while continuing to develop new features that further enhance what is already a formidable collection of applications

Michael Hargreaves

Microsoft Office 365/Dell XPS 15 2-in-1

I’d recommend a Dell XPS 15 2-in-1 and the new Windows 10 to anyone who needs to get serious work done (before you kick back on your couch with your favourite Netflix show.)

Maryellen Rose George

Brother PT-P750W

It’s useful for office tasks as well as pragmatic labelling of equipment and storage – just don’t get too excited and label everything in sight!

Cathy Giles

Brother MFC-L8900CDW

The Brother MFC-L8900CDW is an absolute stand out. I struggle to fault it.

Luke Hill

MSI GT75 TITAN

I need power and lots of it. As a Front End Web developer anything less just won’t cut it which is why the MSI GT75 is an outstanding laptop for me. It’s a sleek and futuristic looking, high quality, beast that has a touch of sci-fi flare about it.

Emily Tyson

MSI GE63 Raider

If you’re looking to invest in your next work horse laptop for work or home use, you can’t go wrong with the MSI GE63.

Featured Content

Don’t have an account? Sign up here

Don't have an account? Sign up now

Forgot password?