Oregon SAP project wracked by leadership woes

The SAP project's costs are now $47 million, nearly triple the original $14 million budget, the city's auditor says

An SAP implementation conducted by the city government of Portland, Oregon, went badly awry due to planning and project leadership problems, resulting in skyrocketing costs and a protracted time line, according to a report released Tuesday by the city's auditor.

The project to replace Portland's existing software with SAP started with a planning phase in 2004 and was originally budgeted at US$14 million, the report states. But while the project has now achieved its primary goal, the implementation ended up costing more than $47 million and took longer than 30 months, instead of an expected 14.

That tab does not include other costs, such as payroll and benefits for many full- and part-time city workers who participated in the project.

SAP and its software did not come under fire in the report.

"The issues that have appeared pre-dated SAP's involvement in this project," said SAP spokesman Andy Kendzie. "To my knowledge, the project is under control and moving forward. They are a very valued customer."

Indeed, the relationship between SAP and Portland appears sound. City officials participated in an SAP case study on the project, and also put out a press release last year extolling the new system's initial benefits.

Instead, the report points to inadequacies on the part of city officials and the project's initial systems integrator.

For example, city officials had based the original budget on an independent estimate that did not factor in costs such as new hardware needed to run the system. In addition, city officials later added more functionality to the project plan.

Meanwhile, the project's contractor, Ariston Consulting and Technologies, "was not always able to identify standardized ways of incorporating these additional items," resulting in higher costs, according to the report.

Ariston also failed to finish project documents on time and had staffing difficulties, it adds.

Portland ultimately terminated its contract with Ariston in 2008 and inked a new deal with SAP's Public Services arm to finish the project, the report adds.

The San Diego systems integrator was acquired by Black & Veatch last year. A representative for the company could not immediately be reached.

Overall, the 14-month planned time line was "too aggressive," and the city went against advice from outside sources, according to the report. One recommendation called for a project schedule of up to four years.

Other issues exacerbated the project's woes as well, such as poorly defined city business processes and the municipal government's decentralized structure, which tied up decision-making in layers of red tape.

Chris Kanaracus covers enterprise software and general technology breaking news for The IDG News Service. Chris's e-mail address is Chris_Kanaracus@idg.com

Join the Good Gear Guide newsletter!

Error: Please check your email address.

Tags business issuesapplicationsenterprise resource planningCIO roleSAPit strategysoftwareIT management

Struggling for Christmas presents this year? Check out our Christmas Gift Guide for some top tech suggestions and more.

Keep up with the latest tech news, reviews and previews by subscribing to the Good Gear Guide newsletter.

Chris Kanaracus

IDG News Service

Most Popular Reviews

Follow Us

Best Deals on GoodGearGuide

Shopping.com

Latest News Articles

Resources

GGG Evaluation Team

Kathy Cassidy

STYLISTIC Q702

First impression on unpacking the Q702 test unit was the solid feel and clean, minimalist styling.

Anthony Grifoni

STYLISTIC Q572

For work use, Microsoft Word and Excel programs pre-installed on the device are adequate for preparing short documents.

Steph Mundell

LIFEBOOK UH574

The Fujitsu LifeBook UH574 allowed for great mobility without being obnoxiously heavy or clunky. Its twelve hours of battery life did not disappoint.

Andrew Mitsi

STYLISTIC Q702

The screen was particularly good. It is bright and visible from most angles, however heat is an issue, particularly around the Windows button on the front, and on the back where the battery housing is located.

Simon Harriott

STYLISTIC Q702

My first impression after unboxing the Q702 is that it is a nice looking unit. Styling is somewhat minimalist but very effective. The tablet part, once detached, has a nice weight, and no buttons or switches are located in awkward or intrusive positions.

Latest Jobs

Shopping.com

Don’t have an account? Sign up here

Don't have an account? Sign up now

Forgot password?